Planned Maintenance region DX1 (Dubai) for w.4 2023-01-23 08.00 CET Maintenance window ends: 2023-01-27 17.00 CET
Scheduled Maintenance Report for Cleura Public Cloud
Completed
The scheduled maintenance has been completed.
Posted Jan 27, 2023 - 17:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 23, 2023 - 08:01 CET
Scheduled
Dear Valued Customer,
Cleura would like to inform you that we have planned maintenance as scheduled below.


Customer intervention will not be required.
Region/datacenter: OpenStack region DX1 (Dubai, UAE)

Maintenance window starts: 2023-01-23 08.00 CET
Maintenance window ends: 2023-01-27 17.00 CET

Maintenance Scope:
Throughout the maintenance window, a number of improvements will be implemented - from functionality to security alignment.

The major part of the scope is the upgrade of the Block and Object Storage services.

Our ambition is to carry out the majority of the maintenance window with little to no impact on running services.

Infrastructure services will be restarted in a controlled and timely manner in order for proper security patching.


Expected customer impact:
- From 2023-01-23 (08:00 CET) to 2023-01-27 (17:00 CET), customers may experience higher latency towards storage.


Follow the status at https://www.cnstatus.com/ for updates.

If you have further questions, please contact our support at support@cleura.com or via your portal login.

Respectfully,
Cleura
Posted Jan 10, 2023 - 17:17 CET
This scheduled maintenance affected: DX1 (Dubai) (API, Network, Compute, Block Storage, Object Storage).