Region FRA1: Planned Maintenance, week 36 - Day 2, part 2
Scheduled Maintenance Report for Cleura Public Cloud
Completed
The scheduled maintenance has been completed.
Posted Sep 03, 2024 - 21:30 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 03, 2024 - 17:30 CEST
Scheduled
Today's second part of the maintenance window starts: 2024-09-03 at 17:30 CET and will continue until 21:30 CET.

  • During this maintenance window, we anticipate impact to our network as we upgrade our network nodes. This will be noticed through short network outages (from a few seconds up to 30 seconds) and re-connection of your VPN tunnels.
  • Posted Sep 03, 2024 - 00:12 CEST
    This scheduled maintenance affected: FRA1 (Frankfurt) (API, Network, Compute, Compute (Local Storage)).